Orion Minerals has received the first US$6.7 million drawdown under its prepayment agreement with Glencore, releasing the first construction money for its Prieska Copper Zinc Mine (PCZM) in South Africa's Northern Cape.
The JSE- and ASX-listed company said on 20 November that the funds will let early construction work begin at the Prieska Uppers mine, with full construction of the Uppers scheduled to start in January 2027.
From signed deal to cash on site
“The company's transition to a base metals producer is now firmly underway, with first concentrate production expected by the end of 2027.” — Tony Lennox, managing director and CEO, Orion Minerals
The drawdown comes from the US$40 million Tranche A, which became unconditional on 19 October. Tranche A is part of the US$250 million financing and offtake agreements between Glencore and Orion's subsidiary, Prieska Copper Zinc Mine (Pty) Ltd. In October, Orion had said it expected the first drawdown by the end of that month.
Orion managing director and CEO Tony Lennox said the receipt of the first Glencore funds was "a big step forward for Orion and PCZM", adding that the company's move to becoming a base metals producer is now under way, with first concentrate expected by the end of 2027.
Lennox said the immediate focus is on starting early site works before the December 2026 break, finalising and awarding key contracts and mobilising personnel. Orion has already picked Torque Africa for drilling and ENPROTEC to deliver the 20,000 tonnes a month Uppers concentrator.
The bigger prize is the Deeps
The larger US$210 million Tranche B, meant for the construction and start-up of the Deeps, remains conditional, and Orion says it is still talking to funding partners about the rest of the money needed to develop the Deeps. Under the offtake terms, Glencore takes all bulk concentrate from the Uppers for five years and all copper and zinc concentrate from the Deeps for at least ten years.
According to Mining Weekly, Prieska produced more than 430,000 t of copper and one million tonnes of zinc from 46.8 Mt of ore milled before it closed in the 1990s. The planned operation could reach steady-state output of 22,000 t of copper and 65,000 t of zinc a year, with the Uppers phase running for about four years and the Deeps for 11 years after dewatering and shaft refurbishment. In May, the Industrial Development Corporation converted its R344.5 million convertible loan into equity in the PCZM holding company.
Why it matters
Prieska is one of the few new base metals mines close to construction in South Africa. Cash on site in the Northern Cape means contracts, local jobs and, if the Deeps financing follows, a new domestic source of copper and zinc concentrate from the end of 2027.
Source: Orion Minerals ASX/JSE release, 20 November 2026; Mining Weekly; Mining Review Africa.