Sylvania Platinum is ending its Thaba joint venture in Limpopo after its mining partner repeatedly delivered less ore, at lower grades and higher cost, than the plan required. The AIM-listed PGM and chrome producer said on 25 November that its South African subsidiary, Sylvania Metals, has invoked the termination clause in the joint venture agreement.
The partner is Limberg Mining Company, a subsidiary of ChromTech Mining Company. Under the deal, announced in August 2023, Limberg mined and supplied run-of-mine ore and historical chrome tailings, while Sylvania built and ran the chrome and PGM processing plants as joint venture manager.
Why Sylvania walked away
Sylvania said run-of-mine tonnages and chrome and PGM feed grades have stayed below plan since commissioning, while mining costs came in significantly higher than planned. The shortfall in ore supply counts as a termination event under the agreement, and the two parties could not agree on a revised basis to keep the venture going. The termination letter went out on 25 November and takes effect on 24 December 2026, 20 business days later.
US$51.1 million owed
Sylvania funded all of Thaba's upfront capital, including Limberg's 50% share, through an interest-bearing loan of about US$32.5 million as at 31 October, interest included. It also covered Limberg's share of working capital through a second loan of about US$18.6 million. The combined US$51.1 million becomes due when the termination takes effect and is secured by special notarial bonds over Limberg's chrome tailings resource. Sylvania said it intends to pursue recovery of the amounts owed.
Limberg keeps the mining right and the infrastructure needed to keep mining, but is no longer obliged to send ore to the plant.
What happens to the plant
Sylvania has an option to keep treating the historic tailings storage facility on site, and future tailings from Limberg, under a use and access agreement that lets it run the relevant sections of the plant. The company said the historic tailings alone could keep on-site operations going for at least four to four and a half years. Thaba will be folded into Sylvania Dump Operations, its six chrome beneficiation and PGM plants, which Sylvania said are unaffected.
Guidance and balance sheet
Sylvania kept its 2027 financial year PGM guidance at 85,000 to 95,000 ounces of 4E PGMs but cut chrome concentrate guidance to 75,000 to 85,000 tonnes, from 110,000 to 140,000 tonnes. It had US$81.4 million in cash at 31 October, which it said gives it room to manage the change and look at other feed sources. The announcement was made by chief executive Jaco Prinsloo.
Why it matters
Thaba added fresh run-of-mine ore to a business built mostly on retreating chrome tailings. Its unwinding shows how much mid-tier chrome and PGM projects in South Africa depend on the mining partner delivering tonnes and grade, and it removes about a third of Sylvania's planned chrome output for the year.
Sources: Sylvania Platinum, "Update on Thaba Joint Venture" (25 November 2026); Mining Weekly.